Quarry first approved in 1987
The quarry was approved by Council in July 1987, subject to conditions. The approval was for 3 years and made provision for subsequent extensions of the approval by Council. It was also subject to some roadwork requirements and included the requirement for a Management Plan to be lodged with Council.
The applicant appealed Council’s decision, with the Local Government Court issuing a Court Order in May 1988 reducing the extent of roadworks required and giving an operating life of 30 years. In terms of road improvements, the conditions of approval required:
- upgrading of the intersection of Sheppersons Lane and Kin Kin Road;
- upgrading of the existing timber bridge within Sheppersons Lane; and
- the widening and upgrading of Sheppersons Lane from intersection with Kin Kin Road to the access point to the site.
These road upgrade works were subsequently undertaken by the former Noosa Council, around the time Noosa Council had a lease over the quarry site. Notably, the requirement to upgrade the intersection of Sheppersons Lane with Kin Kin Road was a requirement of the Main Roads Department at the time, as Council’s Shire Engineer sought their advice in relation to the application as part of the assessment.
The conditions of approval also require the performance of regular maintenance of roadworks within Sheppersons Lane, including the removal of any materials which may fall from vehicles transporting quarry materials.
The conditions do not include an annual tonnage limit on excavation, but do require the quarry to operate in accordance with a Management Plan addressing location of siltation ponds, the extent of proposed excavations, access, location of crusher and office, buffers to adjoining properties boundaries and rehabilitation procedures. In 1991, a Management Plan for Ready Mix was approved.
Extension to Term of Quarry
In 2003, Council extended the term of the quarry until 12 May 2033, subject to conditions. These conditions required the submission of an updated Management Plan. In 2005, an updated Management Plan by the Neilsen Group was approved by Council. It identified a similar quarry footprint to the 1991 Management Plan, with the quarry to be quarried from the top down.
First Breach Action
In September 2010, officers issued a Show Cause Notice to the operators, requiring that the conditions of the development approval be complied with. At the time, there was significant community concern over the operations of the quarry, and inspections indicated that the quarry was not being operated in accordance with the approved Neilsen Group Management Plan. The operators challenged Council’s Show Cause Notice and, due to the non-specificity of the 2005 Management Plan, Council could not proceed further with this action.
Amended QMP lodged
In December 2011, an amended Management Plan was submitted by the quarry operator, seeking to commence quarrying at the bottom of the hill and then proceed to the hilltop and quarry down. This Management Plan provided a greater amount of detail to that contained in the previously approved Management Plan for the site, but maintained a degree of flexibility in relation to the operation, recognising that quarry operations are an evolving process affected by the nature of the extracted resource and market demand for material.
Kin Kin Community Group Action
In October 2010, the Kin Kin Community Group contested the quarry approval, asking the Planning & Environment Court:
- Whether the town planning consent approval given by Noosa Shire Council in 1987 was lawfully given;
- Was the order made by the Local Government Court on 13 May 1988, allowing the appeal against some conditions to which the Noosa Shire Council subjected its approval and varying conditions, made within jurisdiction;
- In the event the approval of the Council was lawfully given and the Court’s orders were within its jurisdiction, did the town planning consent approval lapse; and
- In the event the approval has not lapsed, is use of the site for quarry purposes for extractive industry, limited to the area and scale of development particularised in the application for town planning consent and the town planning consent limited only until 2018.
The judge dismissed all of the Group's claims in December 2010.
Environmental Protection Order Issued
In early 2011, the Department of Environment and Resource Management issued an Environmental Protection Order to the operators of the quarry through their Environmentally Relevant Activity permit. The Environmental Protection Order specified that no further material was to be extracted from the quarry on a commercial basis until a number of steps had been undertaken, including the implementation of appropriate stormwater management measures. In January 2012, the Department of Environment and Resource Management informed the applicant that the Department was satisfied all actions had been completed regarding the Environmental Protection Order, and all activities must be undertaken in accordance with the Environmentally Relevant Activity permit.
The Environmentally Relevant Activity Permit allows for the extraction of up to 1,000,000 tonnes a year. In March 2014 the Department of Environment and Heritage Protection revised the water management conditions over the previous environmental licence.
Approval of Amended QMP
In July 2012, the Sunshine Coast Regional Council resolved to approve, in part, the amended Quarry Management Plan for the initial quarry development phase, given a feasible Stormwater Management Plan was only included for that phase. This meant that the Management Plan will be required to be further updated in the future and approved by Council before further quarrying stages proceeded. The Council also requested a number of amendments to be made to the Management Plan.
At its Ordinary Meeting on 23 May 2013 Council considered further amendments to the Quarry Management Plan and resolved again to approve the plan in part, subject to 8 amendments being made to the Management Plan.
At its Ordinary Meeting on 19 September 2013 Council considered a further amendment to the Quarry Management Plan in relation to the haul route, with Council maintaining the previously approved haul route.
Breach Action in 2014-2016
In late 2014 complaints were received that the quarry operators had blasted the lower foothill area (’the finger’), which is predominantly outside of the approved short term development area footprint and in part outside the long term approved footprint of the excavation area. The matter was reported to Council and an application to the Planning & Environment Court was subsequently lodged. The application sought orders from the Court that excavation is not permitted outside the approved excavation footprint and that works undertaken outside the approved footprint were in breach of the approval.
During the course of Council’s application to the P&E court, the quarry operators also made an application to the P&E Court to change the quarry approval and incorporate a new management plan into the conditions of approval. The changes sought to consolidate all the approvals, including the Extension to Term of Approval into one document for ease of reference and delete, amend existing conditions and include additional requirements. A new condition to comply with the management was of significant benefit to the Council with respect to its enforcement obligations and future dealings with the quarry operators. It overcame a flaw in the original approval which undermined the Council’s ability to enforce the QMP or effectively regulate the quarry’s operations, removing the uncertainty. It also meant future changes to the QMP must also be by way of a statutory development application process.
The amended QMP also provided for an annual audit to be undertaken of the quarry by an independent specialist on behalf of Council but paid for by the operators. Council consequently resolved to not continue with their application, and settle the operator’s application to the court. A Deed of Agreement was also entered into to pay Council’s costs in the matter and payment of $30,000 to an appropriate land management fund.
Since then officers have undertaken regular inspections of the quarry activities as workload permits.
Breach Action in early 2020
In early 2020, after a large rain event, complaints were received from residents that dirty water was coming from the quarry site. Inspection by officers and the state found a significant breach, with the quarry operator extending the excavation area without first extending the necessary stormwater management controls. The operators were issued an Enforcement Notice and infringement notice by officers. The operators have since complied with all actions required by the Enforcement Notice and the fine will be collected through SPER.