Work in Progress

Roadwork ahead sign
Library photo

Some projects/roadworks may take a bit longer than anticipated to complete due to extended periods of rain, or contractors being unavailable. Current capital improvement projects are listed here. Other minor capital projects may also be underway.

Choose the suburb or area to see all work being undertaken in that area:

  • Location: Noosa Shire Pathways
    Project:

    Council plans to upgrade pathways in Tewantin and Noosaville over the next two months to enhance community connectivity. Additionally, two crucial missing pathway links in Tewantin and Cooroy will be completed as part of the Council’s Missing Links initiative, which aims to meet the community's increasing demand for new and improved pathways throughout the region.

    • Cooroy Noosa Road, Tewantin (completed)
    • Griffith Ave, Tewantin (completed)
    • Kauri St, Cooroy (completed)
    • Quota Park, Noosaville (works commence November)
    Start date: September through to November.
    Related document:
  • Location: Black Mountain Landslide
    Project:

    Black Mountain Road:

    In early September, the soil nail crew moved onto the installation of almost 70 anchor-like structures upslope, which is to further support the concrete structure.

    The site continues to be highly constrained with piling rigs, cranes, soil nail rig, concrete trucks and general earthmoving equipment. For this reason, site access cannot be permitted for nonconstruction traffic, including during the Christmas shutdown period.

    For the latest information please see Project News.or the Black Mountain Road page.

     

     

     

  • Location: Boreen Parade
    Project:

    Contractors will soon commence minor stormwater works at the boat ramp area 
    on Boreen Parade opposite the Yacht  Club.

    Council is being advantageous to use an asphalt crew that is available in the 
    locality to expedite the works.

    The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

    Start date: 18 November 2024
    Duration: Two days, subject to weather and construction conditions.
    Related document:
  • There are no capital projects at this time.

  • There are no capital projects at this time.

  • There are no capital projects at this time.

  • Location: Cooroy Hinterland Playground
    Project:

    The Hinterland Adventure Playground in Cooroy will be CLOSED for two weeks from Monday, 28 October 2024 for general maintenance, slide replacement and equipment servicing.

    Council has programmed several aspects of essential maintenance works as part of this closure to ensure this very busy and popular playground is sustained to a high standard

    Related document:
    Location: Musa Vale Road
    Project:

    Designs and tender documentation are being prepared to reconstruct the road edge on the single-lane section of Musa Vale Road, Cooroy. This section of road was damaged during a landslip caused by the major flooding event in February/March 2022.

    The next steps of the project include:

    • design revision
    • design concept submission for QRA funding approval
    • final design development
    • invitation to tender
    • reconstruction of road asset.

    For further information please visit the Disaster Recovery 2022 Floods page

    Related document:
  • There are no capital projects underway at this time.

  • There are no capital projects at this time.

     

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

     

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • Location: Noosa Junction
    Project:

    Contractors will conduct further proactive tree work around Noosa Junction.

    Affected roads are:

    • Noosa Drive, from Coral Tree Avenue to Grant Street.
    • Sunshine Beach Road, from Noosa Drive to Cooyar Street.

    The work will be undertaken during the day between the hours of 6.30am and 4.30pm.

    Start date: 13 November 2024
    Duration: One day, subject to weather and construction conditions.
    Related document:
    Location: Noosa Heads Surf Club - Public Amenities N28
    Project:

    Council will soon undertake essential maintenance on the public shower facilities beneath the Noosa Heads Surf Club. 

    The entire amenities block will be closed for the duration of the works.

    Start date: 5 November 2024
    Duration: Three days, subject to weather and construction conditions.
    Related document:

     

     

     

     

     

     

  • Location: Temporary Large Ferry Closure
    Project:

    Council will be temporarily closing the large ferry to conduct essential maintenance on its 
    landings. This work is necessary to ensure the continued safety and efficient operation of 
    the ferry service. Please note that during this period, only the smaller (12 vehicle) ferry will 
    be available to transport passengers across the Noosa River.

    The scheduled maintenance work on the large ferry landings is planned to take place 
    from Tuesday, 26th November to Thursday, 28th November.

    Start date:  26 November 2024
    Duration: Completion expected by 29 November, weather and construction conditions permitting.
    Related document:
    Location: Teewah Village
    Project:

    In response to community requests, Council has identified several streets in Teewah for maintenance grading and gravel works. This investment in Teewah’s infrastructure will enhance road stability, safety, and accessibility for all residents.

    The work will be undertaken during the day between the hours of 6.30am and 3.30pm.

    Start date:  28 October 2024
    Duration: Completion expected by early November, weather and construction conditions permitting.
    Related document:
  •  

    Location: Eumundi Noosa Road
    Project details:

    Contractors will soon commence road resurfacing works on Eumundi Noosa Rd, Noosaville.

    The work will be undertaken at night between the hours of 6.30pm and 6.30am.

    Start date: 22 October 2024
    Duration: One week, weather and construction conditions permitting
    Related document:
    Location: Gympie Terrace Park Furniture
    Project details:

    Council will soon commence refurbishment of the timber furniture along Gympie Terrace starting at the Pirate Playground and moving towards the Howard Street end.

    The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

    Start date: 4th November 2024
    Duration: Completion by 19th November 2024, weather and construction conditions permitting
    Related document:
    Location: James Street
    Project details:

    Contractors will soon commence kerb and channel wok on James Street Noosaville. 

    The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

    Start date: 14 November 2024
    Duration: Completion expected by 15 December 2024, weather and construction conditions permitting
    Related document:
  • Location: Peregian Beach Skate Park
    Project details:

    Council has engaged Concrete Skate Parks to upgrade the popular Peregian Beach Skate Park. 

    Work began in July 2024 and is anticipated for completion in October 2024.

    During this period, the skate park will be closed for safety reasons, and safety barriers will be installed to restrict access.

    Start date: July 2024
    Duration:Three Three months, subject to weather and construction conditions
    Related document:

     

  • There are no capital projects underway at this time.

  •  

     

  • There are no projects at this time.

     

     

  • Location: Old Ceylon Road
    Project:

    Noosa Council is pleased to advise FKG Civil Pty Ltd has now completed reconstruction works, with the road now restored to normal operation.

    See the Project News [1.03 MB] for all the latest information.

    Location: Ridgewood Road
    Related documents:

    For further information please visit the Disaster Recovery 2022 Floods page

     

     

  • Location: Tewantin Splash Park
    Project:

    Council will soon commence maintenance works to the rubber surface at the Tewantin Splash Park located next to the Noosa Marina

    Every effort will be made to minimise the impact on public, however the splash park will be CLOSED for the duration of the works

    The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

    Start date: 18 November 2024
    Duration: Two days, subject to weather and construction conditions.
    Related document:
  • There are no capital projects underway at this time.

  • Location: Upper Pinbarren Creek Road
    Project details:

    Contractors have started work to undertake flood reconstruction on nine sites from 376 to 516 Upper Pinbarren Creek Road. These works will help provide long-term stabilisation of the road. 

    Construction will generally be completed between Monday and Saturday, 6.30am6.30pm.

    Start date: July 2024.
    Duration: Six months, subject to weather and contruction conditions.
    Related document: